Disclaimer

Please note that you are now entering a website directly or indirectly maintained by a third party (the "External Site") and that you do so at your own risk.

Galiano Gold Inc. (“Galiano”), has no control over the External Site, any data or other content contained therein or any additional linked websites. The link to the External Site is provided for convenience purposes only.

By clicking “Accept” you acknowledge and agree that neither Galiano nor third party provider Virtua Research, Inc. (“Virtua) is responsible, or accepts or assumes any responsibility or liability whatsoever for, the content, the data or the technical operation of the Linked Site. Further, by entering the External Site, you also acknowledge and agree that you completely and irrevocably waive any and all rights and claims against Galiano and Virtua and further acknowledge and agree that in no event shall Galiano or Virtua, its officers, employees, directors and agents be liable for any (i) indirect, consequential, incidental, special, compensatory or punitive damages, (ii) damages for loss of income, loss of business profits, business interruption, loss of data or business information, loss of or damage to property, (iii) claims of third parties, or (iv) other pecuniary loss, arising out of or related to this disclaimer or the External Site

By entering the External Site, you further acknowledge and agree that the disclaimer of warranties and limitations of liability set out in this disclaimer shall apply regardless of the causes, circumstances or form of action giving rise to the loss, damage, claim or liability, even if such loss, damage, claim or liability is based upon breach of contract (including, without limitation, a claim of fundamental breach or breach of a fundamental term), tort (including, without limitation, negligence), strict liability or any other legal or equitable theory, and even if Galiano and Virtua are advised of the possibility of the loss, damage, claim or liability. The waiver and release specifically includes, without limitation, any and all rights and claims pertaining to the processing of personal data, including but not limited to any rights under any applicable data protection statute(s).

If in any jurisdiction, any part of this disclaimer is held to be unenforceable by a court of competent jurisdiction, such part of this disclaimer shall be restricted or eliminated to the minimum extent and the remaining disclaimer shall otherwise remain in full force and effect.

Please note the information presented is deemed representative at the time of its original release. Changes in historical information may occur due to adjustments in accounting and reporting standards & procedures.

Non-GAAP Information

In addition to disclosing results determined in accordance with GAAP, Galiano may also disclose certain non-GAAP and pro forma non-GAAP results of operations, including certain ratios, operational and miscellaneous data, as well as net income, diluted earnings per share, operating expenses, and operating income that make certain adjustments or exclude certain charges and gains that are outlined in the schedules included in this website. Management believes that this non-GAAP and pro forma non-GAAP information provides investors with additional information to assess Galiano’s operating performance by making certain adjustments or excluding costs or gains and assists investors in comparing our operating performance to prior periods. Management uses this non-GAAP and pro forma non-GAAP information, along with GAAP information, in evaluating its historical operating performance. Galiano and Virtua also take no responsibility for third party pricing data provided for informational purposes and certain ratio results formulated from the provided third party pricing data.

The non-GAAP information is not prepared in accordance with GAAP and may not be comparable to non-GAAP information used by other companies. The non-GAAP information should not be viewed as a substitute for, or superior to, other data prepared in accordance with GAAP.

News Details

Asanko Gold Mine Announces First Gold Production

January 27, 2016

Related documents

VANCOUVER, BRITISH COLUMBIA—(Marketwired - Jan. 27, 2016) -

Highlights:

  • First gold poured on January 26, 2016

  • Designed hourly throughput rates and mill grind attained in both SAG and Ball Mills

  • Ramp-up to commercial production remains on track for Q2 2016

Asanko Gold Inc. (“Asanko” or the “Company”) (TSX:AKG)(NYSE MKT:AKG) announces first gold production of approximately 400 ounces from Phase 1 of the Asanko Gold Mine (“AGM” or the “Project”) in Ghana. This follows the successful commencement of operations of the entire processing facility one month ahead of schedule. The latest videos and photographs are available at http://www.asanko.com/projects/photo-gallery.

Commenting on this historic milestone, Peter Breese, President and CEO, said: “I am proud to announce that the Asanko Gold Mine is officially the newest producing gold mine in Ghana, with Phase 1 successfully built within our capital budget and commissioned one month ahead of schedule.

“As we embark on a new chapter for Asanko, I’d like to thank the Government and our stakeholders in Ghana for all their assistance in facilitating our transition from explorer to producer. In addition I would like to commend my team, our EPCM contractor DRA Global and all the thousands of construction and service sub-contractors for delivering a well-executed project over the past 18 months.

“As we complete commissioning and ramp up to steady-state production rates, I am pleased to note the early gains that we have already achieved with respect to throughput rates and mill grind, which have exceeded our expectations. We remain confident of declaring commercial production during Q2 2016.”

Commissioning and Ramp-Up

Commissioning of the processing facility is progressing well and is approximately one month ahead of the original schedule. The crusher was handed over from the EPCM contractor to Asanko in mid-December and was commissioned during the last half of the month. Ore was stockpiled ahead of the milling operations and introduced into the SAG and Ball mills during the last week in December.

Commissioning of the mills was initially conducted on marginal grade ore until the mills achieved the designed hourly throughput rates and grind. The mills have had several days of continuous operations with daily milling rates matching or exceeding designed throughputs of 8,300 tonnes per day. In addition both mills have also attained grinds that are in line with the plant design parameters.

The operations were fed low grade ores until the density built up in the fully erected and commissioned CIL circuit. Once this was achieved, cyanide was introduced into the CIL and gravity gold circuits and the entire operation from milling to the CIL circuit is now being run at planned feed grades. Gold inventory in the CIL circuit will continue to build up to steady-state levels over the next month, after which time full gold production rates are expected to be reached. Commercial production is expected in Q2 2016.

Mining

The development of the Nkran pit continues to advance well with full drill and blast operations continuing at long-term steady state levels. To date, over 22 million tonnes of material has been removed from the pit and various ore benches have been exposed. There are now enough working faces available in the pit to facilitate mining of the requisite quantities of ore at planned grades to feed the mill at designed throughput rates.

Grade control drilling is proceeding according to plan with the next six months of planned ore having been drilled and modelled into the medium term mine plan. The grade control based mine plan for 2016 is expected to be in-line with the Definitive Project Plan, which was published in November 2014.

Cash Position

The Company has a strong balance sheet with US$116 million cash on hand, as at December 31, 2015.

About Asanko Gold Inc.

Asanko’s vision is to become a mid-tier gold mining company that maximizes value for all its stakeholders. The Company’s flagship project is the multi-million ounce Asanko Gold Mine located in Ghana, West Africa. The mine is being developed in phases. Phase 1 has been commissioned, with first gold produced in early Q1 2016. Ramp-up to steady state production of 190,000 ounces per annum is expected in Q2 2016.

Asanko is managed by highly skilled and successful technical, operational and financial professionals. The Company is strongly committed to the highest standards for environmental management, social responsibility, and health and safety for its employees and neighbouring communities.

Forward-Looking and other Cautionary Information

This release includes certain statements that may be deemed “forward-looking statements”. All statements in this release, other than statements of historical facts, that address estimated resource quantities, grades and contained metals, possible future mining, exploration and development activities, are forward-looking statements. Although the Company believes the forward-looking statements are based on reasonable assumptions, such statements should not be in any way construed as guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices for metals, the conclusions of detailed feasibility and technical analyses, the timely renewal of key permits, lower than expected grades and quantities of resources, mining rates and recovery rates and the lack of availability of necessary capital, which may not be available to the Company on terms acceptable to it or at all. The Company is subject to the specific risks inherent in the mining business as well as general economic and business conditions. For more information on the Company, Investors should review the Company’s annual Form 20-F filing with the United States Securities Commission and its home jurisdiction filings that are available at www.sedar.com.

Neither Toronto Stock Exchange nor the Investment Industry Regulatory Organization of Canada accepts responsibility for the adequacy or accuracy of this release.

Asanko Gold Inc.
Alex Buck
Manager, Investor and Media Relations
Toll-Free (N.America): 1-855-246-7341
+44-7932-740-452
alex.buck@asanko.com

Asanko Gold Inc.
Wayne Drier
Executive, Corporate Development
+1-778-729-0614
wayne.drier@asanko.com

Asanko Gold Inc.
info@asanko.com
www.asanko.com